CONSTRUCTION UPDATE
Published: 1st November 2018
The Loom at Vulcan Mill is making good progress with the piling now fully finished and pile caps installed. The basement slab has been fixed and all ground beams are therefore completed. The installation of beams has allowed work to commence on the installation of the steel frame, enabling further concreate slabs from the ground floor to be placed.
The most resent stage of construction on The Loom at Vulcan Mill is the installation of the ground floor concrete supporting walls, which continue to progress.